Common Scenarios #

Scenario 1: Weekend Sale #

Goal: Run discounts Friday through Sunday

StepWhat to Do
1Click Start field, select Friday
2Click End field, select Sunday
3Check badge is Blue (Pending) or Green (Active)

Result: Discounts run from Friday 00:00 until Sunday 23:59:59 (the entire Sunday is included).


Scenario 2: Rest of This Month #

Goal: Run until end of current month

StepWhat to Do
1Click on Start field
2Click “This Month” button

Done! Both dates fill automatically (today through month end).

Edge case: If today is the last day of the month, both Start and End will be set to Today.


Scenario 3: All Next Week #

Goal: Schedule for next week

StepWhat to Do
1Click on Start field
2Click “Next Week” button

Result: Badge shows Blue (Pending), then turns Green when next week starts.


Scenario 4: Today Only (Flash Sale) #

Goal: Discounts just for today

StepWhat to Do
1Click Start, click “Today”
2Click End, click “Today”

Result: Runs until 23:59:59 tonight, then becomes Gray (Completed) tomorrow morning.


Scenario 5: Pause and Resume #

Goal: Stop discounts temporarily, then restart

To PauseClick toggle to OFF → Badge turns Red
To ResumeClick toggle to ON → Badge turns Green

Troubleshooting #

Problem: Badge stays Yellow #

Cause: Missing dates

Fix: Make sure BOTH Start and End are filled.


Problem: Can’t select past dates #

This is normal. Start date cannot be in the past.


Problem: Toggle doesn’t respond #

Cause: Your badge is Blue, Gray, or Yellow

Fix: Toggle only works when badge is Green or Red.


Problem: Toggle moves then snaps back #

Two possible causes:

What HappensCauseFix
Snaps back silentlyStatus is lockedCheck badge color (must be Green/Red)
Snaps back with error messageConflict with another groupChange dates or products to avoid overlap

Problem: Can’t activate – conflict error #

Cause: Another group overlaps with your dates AND products

Fix options:

  1. Change your dates to not overlap
  2. Pause the other group first
  3. Change product selection in one of the groups

Problem: Week button gives wrong days #

Cause: WordPress week setting is different

Fix: Go to Settings → General → Week Starts On


Problem: “This Month” sets same day for Start and End #

This is normal if today is the last day of the month. The button sets from “today” to “month end” — if those are the same day, you get a single-day campaign.


Before Going Live Checklist #

  •  Start date is set
  •  End date is set
  •  Badge is Green or Blue
  •  Group has at least one rule
  •  No conflict errors

Quick Reference #

I Want To…Do This
Start todayClick “Today” for Start
Run all monthClick “This Month”
Schedule aheadSet future Start date
Pause temporarilyToggle OFF
ResumeToggle ON
End earlyChange End date to today